Cycle 1, private buildings
Privately owned buildings of 50,000 square feet and larger.
Washington, DC Building Energy Performance Standards
Buildings below the District's standard had to improve during Cycle 1. Falling short can cost up to $10 per square foot of gross floor area, capped at $7.5 million per building and scaled to how far short the building falls. We help owners close out Cycle 1 and get ready for Cycle 2.
BEPS applies to buildings that benchmark in the District and fall below the standard for their property type.
Privately owned buildings of 50,000 square feet and larger.
District-owned buildings of 10,000 square feet and larger.
The threshold drops to 25,000 square feet in Cycle 2 and to 10,000 square feet in Cycle 3.
Fast, low-cost savings first, and evidence your filing can stand on.
Where the building stands against the standard, which pathway it is on, and what is still reachable before December 31.
Controls, schedules, setpoints and sequences tuned and verified device by device. Usually the fastest way to cut energy use intensity.
CommissioningThe energy audit the Prescriptive pathway is built on, with our partner PE where a seal is required.
Energy modeling and auditsMeasures, dates, photos and before-and-after data from our record, organized for the Completed Actions Report.
How we prove itWe prepare your 2026 data and coordinate the third-party verification with a qualified, licensed verifier.
Measures, timing and capital plan for the next standard, so Cycle 2 does not start with a gap.
What the close-out looks like with us.
Week 1
Benchmarking history, pathway of record and the size of the remaining gap.
Before December 31
RCx and quick measures in place, and any pathway change applied for.
January to March 2027
Every completed measure documented with dates, photos and data.
By April 1, 2027
Delay or exemption request prepared, if the building needs one.
By May 3, 2027
Completed Actions Report and verified 2026 benchmarking submitted.
On site within 48 hours in DC
We are on site in Washington, DC within 48 hours of the first call. The same engineers who tune your systems for Cycle 1 build the plan for Cycle 2.
Performance, Standard Target, Prescriptive or the Alternative Compliance Pathway. Your pathway of record is in the BEPS portal; we confirm it and check it still fits in the gap check.
You can still apply to change pathways by December 31, 2026, request a delay or exemption by April 1, 2027, and penalties scale with progress, so every measure completed lowers the amount at risk.
We prepare the data and coordinate the verification with a qualified, licensed verifier who meets DOEE's requirements, so the verification stays independent.
Retro-commissioning lowers the energy use intensity the Performance and Standard Target pathways measure, and it is usually the fastest and least costly first step.
January 1, 2028, with the threshold lowered to buildings of 25,000 square feet and larger.
Tell us the building and the pathway you are on. We reply within one business day and can be on site in DC within 48 hours.
Prefer to talk? +1 (646) 296-8091 or [email protected]
Dates and thresholds from DOEE guidance and the Building Innovation Hub as of November 2026. Confirm your building's requirements in the DC BEPS portal.